The Reverence Project, Upcoming Renovations at ICOI: Jan 21 - Feb 20, 2025

Islamic Center of Irvine (ICOI)
MasjidPlus AI
4 months ago

New Carpets, New Lights, New Partitions

As-Salaamu 'alaykum, dear ICOI Community,

May  Allah Subhaanahu wa Ta'aala bless and reward immensely all those who supported and donated towards our ICOI Reverence Project that includes key upgrades, like replacing the carpets.

We are pleased to inform you that the work has begun and is scheduled to continue through February 20, 2025. Some other improvements will include waterproofing, painting, electrical system upgrades, and restroom partition replacements.

While we will strive to minimize disruptions, this project will undoubtedly temporarily impact some of our daily operations. However, Friday prayers will proceed as usual, as the schedule has been adjusted to accommodate them without any interruptions.

Renovation Overview and Key Dates*:

  • Jan 21-23: Waterproofing, drywall installation, and electrical upgrades in multiple areas.
  • Jan 25-30: Main prayer hall preparation, painting, and restroom partition replacements.
  • Feb 1-6: Renovation of the womens prayer area and classrooms.
  • Feb 8-13: Painting of staircases and the main hallway.
  • Feb 15-20: Carpet replacement throughout the facility.

* Please note that this schedule is tentative and subject to adjustments as needed.

We sincerely appreciate your patience and understanding as we work to improve the House of Allah  Ta'aala. If you have any questions or concerns, please feel free to reach out to us at (949) 336-3975.

Thank you for your ongoing support, patience, and cooperation!

Karima Berrada
Director of Operations