Brothers/Sisters,
 
The construction work has picked up last few weeks due to less cold weather. The basement work has about 50% complete - concrete footings complete, basement walls forms on three sides formed, pouring walls next week, elevator well dug up and concrete poured.

This month's construction updates are here - Construction Updates, and also check out a few new construction pictures/videos for the month of February - Construction Pictures.

For more updates please attend the monthly third Friday potluck at the Musallah.

 
-Board of Directors