Assalaamu alaikum!
Dear GIC community members,
The concrete work is done and the road will be ready for use by 7/24.
FYI, the contractor has the following work to complete
Smooth the junction of Main parking lots entry/exit with the new Road
Build 2 ramps to the grassy lot
Finish the drainage opening/exit
Reinstall the RV gate
Add gravel on both sides of the road
Add gravel at the church entrance
Repair the curb (temporary entrance)
We appreciate your patience as we complete the work and open the road to everyone.